OEE Lab / Tools / Throughput Calculator

Throughput Calculator

Enter what the line made and the time it took. You get throughput per hour and per shift against your planned rate, with good units kept apart from total units.

What the line made

Any period works, from one shift to a month. Keep every number on that period.

Good and rejected, counted at the end of the line.
The units you can ship.
h
Planned to run, net of breaks.
h
Every stop while it was meant to run.
h
Turns the hourly rate into a shift figure.
Good units the plan expects per scheduled hour.
Throughput, good units per scheduled hour
-/h
Good units / scheduled hours
0planned rate = full bar
Good units per shift
-
Good units per run hour
-
Total units per sched. hour
-
Seconds per good unit
-
Gap to plan per hour
-
Gap to plan per shift
-
Stops cost per hour
-
Rejects cost per hour
-

Want a second look at this result?

Leave your work email if you would like the OEE Lab team to get in touch about your numbers. To keep the result, use Copy link or Print above.

Thanks, we have your email.

No newsletter, no spam.

Counts typed in at the end of a shift arrive too late to act on.

Fabrico, a light MES for OEE, takes counts, speed and stops live from PLCs or from external IoT sensors on older machines, and shows OEE per line and shift. See it live in Fabrico.

See where your line loses this time: book a demo with a Fabrico consultant.

Request a demo Contact us
Our tools stay free either way.

What you get from your counts and hours

It takes your counts and hours and gives good units per hour and per shift, next to the rate you planned. It also shows how many units per hour stops and rejects took away.

For what the word means and the three time bases in depth, read how to calculate throughput. This page is the tool for your own numbers.

The throughput formula

Throughput rate = good units / scheduled hours
Throughput per shift = rate × scheduled hours per shift
Gap to plan = rate - planned rate
The three lines the calculator runs on.

The throughput rate of a whole line can never beat its slowest step, however fast the other steps run. So count at the end of the line, and do not add machines together.

Example: a packing line over 3 shifts

Example: a packing line runs 3 shifts of 7.5 scheduled hours, so 22.5 hours. It makes 9,000 units, of which 8,640 are good, and stops for 2.5 hours in total.

MeasureWorkingResult
Good units per scheduled hour8,640 / 22.5384/h
Good units per shift384 × 7.52,880
Good units per run hour8,640 / 20432/h
Total units per scheduled hour9,000 / 22.5400/h
Gap to plan per hour384 - 420-36/h
Gap to plan per shift-36 × 7.5-270
The plan is 420 good units per scheduled hour, so the line is 36 an hour short.

Now follow the rate down from the speed the line ran at. While running it made 9,000 / 20 = 450 units an hour.

While running (9,000 / 20 h)450 / h
After stops (9,000 / 22.5 h)400/h
After rejects (8,640 / 22.5 h)384/h
Planned rate420 / h
Stops take 50 units an hour and rejects take 16, which puts the line below the 420 plan.

What the gap to plan is telling you

Good per scheduled hour is the number to promise to shipping, because stops and rejects are already inside it. Good per run hour shows how fast the line goes when it goes.

A big gap between the two means stops are your problem. A big gap between total and good means quality is, and the scrap rate calculator will price it.

Use the split to size a fix before you start it. Halve the stops in the example and the line makes 425 units per scheduled hour, or 408 good at the same 96% yield, still 12 short of plan.

To track the gap through the day, put it on an hour-by-hour production board. Over a whole period the same ratio is plan attainment.

Good units or total units?

Keep both, and do not let one stand in for the other. Total units tell you what the machines did, while good units tell you what the customer gets.

Rejected units took line time and still ship nothing. A report of 400 an hour reads better than 384, but only 384 can go on the truck.

Where throughput figures go wrong

  • Mixing time bases. A planned rate per run hour compared with actual per scheduled hour looks like a loss that never happened. Set the plan on the same base.
  • Using the ideal rate as the plan. The plan should allow for normal losses. Good units per scheduled hour against the ideal rate is OEE, which the OEE calculator handles.
  • Counting at a machine upstream of the bottleneck. It can look fine while the line starves.
  • Mixing units. Cases and bottles do not add up, so pick one unit per line.

If demand sets your plan, get the pace from the takt time calculator, then see takt time vs throughput for how the two differ.

Throughput formula questions

What is the throughput formula?

Throughput = good units / time. 8,640 good units in 22.5 scheduled hours gives 384 units per hour. The definitions and time bases are in how to calculate throughput.

What is the throughput rate formula for a line?

Measured rate is good units divided by hours. The most a line can do is 1 / the cycle time of its slowest step, so a 9-second step limits it to 3,600 / 9 = 400 an hour. Use the cycle time calculator for that side.

How do I turn throughput per hour into throughput per shift?

Multiply the hourly rate by the scheduled hours in a shift. 384 an hour over 7.5 hours is 2,880 units a shift. Use scheduled hours, because the hourly rate already includes the stops.

Should throughput count rejected units?

No. Throughput counts good units, so rejects show up as a lower rate. Keep the total as well, because the gap between total and good is your quality loss.

Why is throughput below plan when the machine runs fast?

The running speed ignores stops and rejects. In the example the line runs at 450 an hour and still delivers 384 good units per scheduled hour. The production capacity calculator shows the same gap in capacity terms.

Is throughput the same as throughput time?

No. Throughput is units per hour, and throughput time is how long one unit takes to get through the process. A line can have a high rate and still a long time per unit if stock waits between steps.