Takt time is the pace demand asks for, in seconds per unit. Throughput is the pace you really deliver, in good units per hour. To compare them, convert takt: required rate = 3,600 / takt. Example: a 40-second takt needs 90 units an hour, so a throughput of 78 misses it by 12 an hour.
One asks, the other answers
Takt comes from the customer and stays the same however well the line runs. Throughput comes from the line, and a bigger order does not make the line any faster.
Neither one tells you much alone. The gap between them tells you whether the plan will be met.
| Takt time | Throughput | |
|---|---|---|
| Question | How often must a unit finish? | How many good units came out? |
| Comes from | Demand and available time | The line, with all its losses |
| Usual unit | Seconds per unit | Good units per hour or shift |
| Moves when | Orders or shift length change | Stops, speed or rejects change |
| Formula | Available time / demand | Good units / time |
We use throughput here for good units over a stated time, as in how to calculate throughput. Some people mean the speed of the slowest step, which is the best the line could do, and throughput time is a different metric again.
How to convert one into the other
Takt is seconds per unit and throughput is units per hour, so you divide one into 3,600. Turn either one around, and they can sit on the same line of a report.
The units per hour calculator does this conversion for you. It helps when one team talks in takt and another in UPH.
Worked example
Example: a hypothetical bottling line has 7.5 available hours, which is 27,000 seconds, and demand for 675 cases a shift. Takt = 27,000 / 675 = 40 seconds, or 90 cases an hour.
The slowest machine has an ideal cycle time of 36 seconds a case, which is 100 cases an hour. The shift delivers 585 good cases, so throughput = 585 / 7.5 = 78 cases an hour.
Three numbers give the whole picture. The ideal rate of 100 says the line can do it, the required rate of 90 says what it must do, and the throughput of 78 says what it did.
Where OEE fits between them
Good units per scheduled hour divided by the ideal rate is OEE, when scheduled hours match planned production time. So here OEE = 78 / 100 = 78%.
The OEE this line needs is ideal cycle / takt = 36 / 40 = 90%. So the line is 12 points short, and with an ideal rate of 100 cases an hour, each point here is one case an hour; how to set OEE targets builds on this.
What happens when demand moves
Takt moves with demand, and the line does not. The same line can look fine in one month and hopeless in the next, and nothing on the floor has changed.
| Demand | Takt | Required rate | OEE needed | At 78 cases an hour |
|---|---|---|---|---|
| 540 | 50.0 s | 72 / h | 72% | 45 cases too many |
| 675 | 40.0 s | 90 / h | 90% | 90 cases short |
| 810 | 33.3 s | 108 / h | 108% | 225 short, and out of reach |
At 810 cases, takt is shorter than the ideal cycle, so no amount of OEE work will meet demand in this shift. Even at the ideal rate, 810 x 36 s takes 8.1 hours, which means more time or more capacity.
At 540 cases, running at full throughput builds stock nobody asked for. The line should stop at the plan, as OEE and seasonal demand and OEE with no orders explain.
The time base trap
Takt uses available time, after breaks and planned stops. So throughput must use the same hours, or the comparison is off before you start.
Example: 585 cases over a full 8 paid hours gives 73.1 an hour, and over the 7.5 available hours it gives 78. Only the second may be set against the 90 from takt.
Likewise, a throughput per run hour leaves the stops out. It tells you how fast the line goes, but it cannot tell you whether you met the plan.
Reading the gap
The plan is safe. Hold the pace and do not build extra stock.
The line can do it, and losses are in the way. Work on stops, slow running and rejects at the bottleneck.
Losses are not the main issue. Add time or capacity, or rebalance the slowest step.
You have spare capacity. Stop at plan, and use the time for changeovers, training and care of the machines.
To find where the losses are, start with the bottleneck and the six big losses. For added capacity, see how to increase production capacity.
How to run this on the floor
- Post both on one board. Show the required rate from takt next to the good count each hour, as on a takt time board.
- Count at the end of the line. A count at a faster upstream machine overstates throughput.
- Recalculate takt when the plan changes. A stale takt makes the whole comparison wrong.
- Use one case size. A pack of 6 and a pack of 12 are not one unit, so convert first.
Traps in the comparison
- Setting takt from throughput. Takt then says whatever the line already does, and it can never show a gap.
- Treating a high throughput as good by itself. Above the required rate, extra units are stock and not sales.
- Comparing takt with ideal cycle time only. A 36-second ideal under a 40-second takt looks safe, and it leaves only 10% room for all losses.
- Mixing in the money meaning. In the Theory of Constraints, throughput means money per unit of time, so it cannot be compared with takt at all.
Compare them on your line
Enter your good units and hours in the throughput calculator, and get takt from the takt time calculator. Then track the two against each other with plan attainment.
To see the gap during the shift, you need a count you can trust. Fabrico takes counts, speed and stops live from PLCs or from external sensors on older machines, and shows OEE per line and shift. See how Fabrico connects machines.
What people ask next
What is the difference between takt time and throughput?
Takt is the pace demand needs, in seconds per unit. Throughput is the pace the line delivered, in good units per hour. Compare them after converting with 3,600 / takt.
How do you convert takt time to units per hour?
Divide 3,600 by takt in seconds. A 40-second takt is 90 units an hour. The units per hour calculator does it in both directions.
Can throughput be higher than takt requires?
Yes, and then the line is building more than was ordered. That stock ties up cash and floor space, so stop at the plan. Use the spare time for changeovers or training.
Is takt time the inverse of throughput?
Only as a formula shape. Takt inverts the required rate, and throughput is the actual rate. They match only when the line delivers exactly what demand asks for.
What if takt time is shorter than my ideal cycle time?
The line cannot meet demand in that available time, even at 100% OEE. Add time or capacity, or cut work from the slowest step. See the line balancing calculator.
Fabrico is a light MES for OEE. It takes stops, speed and counts from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and operators tag the cause at the line.