Your line, one period
Use one shift or one day, and keep every number on that period.
Want a second look at this result?
Leave your work email if you would like the OEE Lab team to get in touch about your numbers. To keep the result, use Copy link or Print above.
No newsletter, no spam.
A shift total says how much was lost, not where it went.
This calculator works from numbers you type in after the shift. Fabrico, a light MES for OEE, takes stops, speed and counts live from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and operators tag the cause at the line. See it live in Fabrico.
Request a demo Contact usWhat line efficiency tells you
Line efficiency tells you how much of the labor you paid for became standard work on good pieces. It suits lines run mostly by people, such as assembly, sewing and hand packing.
For a line paced by machines, use the OEE calculator instead. For the step-by-step method, read how to calculate line efficiency.
The line efficiency formula
Standard minutes produced is good pieces times the standard minutes per piece. Balance loss is 100% minus balance efficiency.
Example: 6 people, 720 pieces, one shift
Example: a 6-person assembly line works a 450-minute shift and makes 720 good pieces. One piece holds 2.40 standard minutes of work, and the slowest station needs 0.50 minutes.
- Standard minutes produced = 720 × 2.40 = 1,728.
- Operator minutes worked = 6 × 450 = 2,700.
- Line efficiency = 1,728 / 2,700 = 64.0%.
- Balance efficiency = 2.40 / (6 × 0.50) = 80.0%, so balance loss is 20.0%.
- Running factor = 720 × 0.50 / 450 = 80.0%, because the bottleneck could pass 900 pieces and the line made 720.
Check it: 80.0% × 80.0% = 64.0%.
The station times below add up to the 2.40 standard minutes. The grey part of each bar is time that operator waits for the slowest station.
Balance loss or running loss: which to fix
Balance loss is built into the layout. It stays the same however well the shift runs, and the fix is moving work off the slowest station with the line balancing calculator.
Running loss is what happened on the day. It holds stops, missing people, slow pace and rework, so log the stops first.
We found no neutral benchmark that fits all lines, because the result depends on the product mix and on how tight your standards are. Compare a line with its own trend, on the same standards.
Getting the inputs on the floor
- Standard minutes: add the timed work of each station, using a cycle time study rather than the fastest timing you saw.
- Good pieces: count at the end of the line, after the final check.
- Minutes worked: count everyone paid to be on the line, including time they spent waiting.
- Two people at one station: divide that station's time by two before you compare it, because the formula works per operator.
Mistakes that skew the number
- Counting all pieces. Rejected pieces earn no standard minutes.
- Using takt or the slowest station as the standard. Standard minutes per piece is the whole work content, so it is much larger than one station's time.
- Leaving out helpers. Fewer operators on paper gives a flattering number.
- Trusting a result over 100%. It usually means loose standards or a miscount, so check both before you celebrate.
Line efficiency, balance efficiency and OEE
Our line balancing calculator gives work content / (stations × cycle time), and some books call that line efficiency too. Here it is called balance efficiency, because it describes the design and ignores what happened on the shift.
OEE measures machine or line time against an ideal rate, while line efficiency measures labor against a standard. See production efficiency vs OEE and OEE for assembly lines.
Line efficiency questions
How do you calculate line efficiency?
Multiply good pieces by the standard minutes per piece, then divide by operators times minutes worked. 720 pieces at 2.40 minutes, with 6 people working 450 minutes, gives 1,728 / 2,700 = 64.0%. The full method is in how to calculate line efficiency.
How do you calculate assembly line efficiency from station times?
Add the station times to get the standard minutes per piece, and take the longest one as the slowest station. Enter both here with your output, and the calculator splits the loss into balance and running. See assembly line efficiency.
What is balance loss?
It is the share of paid time operators spend waiting for the slowest station. Balance loss = 100% minus standard minutes / (operators × slowest station time). In the example, 2.40 / 3.00 = 80%, so the loss is 20%.
Does this work for garment lines?
Yes, the formula is the same, with SAM as the standard minutes per piece. Use the same SAM source each time, or your trend will move for the wrong reason. See garment line efficiency.
Why is my line efficiency over 100%?
Usually the standard minutes are too generous, or the count includes pieces from another period. A result above what the slowest station allows points to a wrong station time. Fix the inputs before you compare lines.
Is line efficiency the same as labor productivity?
They are close but use different units. Line efficiency compares earned minutes with paid minutes, so it can mix products, while units per labor hour counts pieces and only compares like with like.