A takt time board shows the crew four things at the line: takt, the plan count so far, the actual count and the gap. Plan so far = working seconds elapsed / takt. Example: at a 72-second takt, the plan after 3 working hours 45 minutes is 187 units, so 176 made means 11 behind, or 13.2 minutes of work.
What the board is for
A takt board answers one question while there is still time to act: are we ahead or behind right now? A report at the end of the shift can only explain what already happened.
It works when anyone on the line can read it in a few seconds. So four numbers beat a screen full of charts.
How the plan count works
Example: a hypothetical line runs 07:00 to 15:30, with breaks at 09:00 (15 minutes), 11:30 (30 minutes) and 13:30 (15 minutes). That leaves 450 working minutes, or 27,000 seconds.
Demand is 375 units, so takt = 27,000 / 375 = 72 seconds, which is 50 units a working hour. You can check this with the takt time calculator.
The clock must stop during breaks, or the plan keeps climbing while nobody works. So program the break times in, or the board will tell the crew they are behind when they are not.
One morning on the board
| Hour | Plan | Actual | Plan so far | Actual so far | Gap |
|---|---|---|---|---|---|
| 07-08 | 50 | 46 | 50 | 46 | -4 |
| 08-09 | 50 | 49 | 100 | 95 | -5 |
| 09-10 (break) | 37.5 | 36 | 137 | 131 | -6 |
| 10-11 | 50 | 45 | 187 | 176 | -11 |
A gap of 11 units at 72 seconds each is 792 seconds, or 13.2 minutes of work. Saying "13 minutes behind" often lands better on the floor than a unit count.
What is a takt clock?
A takt clock counts down one takt, then resets. On a paced line, each station should finish as it reaches zero.
It helps on a line with long takts, such as several minutes, where nobody can feel the pace. On a 20-second line it just flickers, so a running count serves the crew better.
- Count-up board: shows plan and actual. It suits most lines and needs one count at the end.
- Countdown clock: shows time left in this takt. It suits long-cycle assembly.
- Both: a clock for the pace and a count for the score. It suits a line where one late station holds up the rest.
Three ways to build one
| Type | What it needs | Fits when |
|---|---|---|
| Whiteboard | Marker, hourly plan printed in advance, one person who writes it up | You are starting out, and hourly updates are enough |
| Counter with display | A part counting sensor and a large LED display | You want a live count at one line |
| Screen fed from line data | A screen at the line, plus a source of counts such as PLC signals | You want it on many lines, with history kept |
A whiteboard is the same idea as an hour-by-hour production board, and that guide covers how to run it day to day. This page adds what changes when takt itself is on display.
Rules that keep it honest
- Count good units at the end of the line. A count taken earlier hides the rejects.
- Set takt from demand. If it was set from what the line can do, the board can never show a real gap.
- Change takt when the plan changes. If demand moves to 400 units, takt is 67.5 seconds, or 53.3 units an hour, and the board has to show it.
- Fix a rule for changeovers. Decide whether the plan pauses, and keep to it, since how to count changeovers in OEE faces the same choice.
- Treat being ahead as a signal too. A line far ahead of takt is building stock nobody asked for yet.
What to do when the gap grows
Agree the trigger in advance, so that nobody needs to decide under pressure. Example rule: at a gap of 5 units, the team leader goes to the line, and at 10 units, the supervisor does.
Write the reason next to the hour, even in two words. The notes feed the daily production meeting, and an andon call can bring help sooner.
How good boards go stale
- Showing OEE in place of takt. OEE is a fine shift figure, and the crew still needs a count they can act on right now.
- Mounting it where only managers walk. Test it from the farthest station on the line.
- Too small a font or too many numbers. If you need to walk up to read it, it will not get read.
- One takt on a mixed line. When models take different work, an average takt can mislead, so use the mixed-model takt time calculator and plan by sequence.
- Using the board to blame. If a gap brings only trouble, the count starts to bend.
A board is only as good as its count. Fabrico takes counts, speed and stops live from PLCs or from external sensors on older machines, so the count at the line is not written up by hand. See how Fabrico connects machines.
What people ask next
What should a takt time board show?
Takt, the plan count so far, the actual count and the gap. Add a line for the reason when the gap grows. Keep it readable from the far end of the line.
How do you calculate the plan count on a takt board?
Divide the working seconds elapsed by takt, and leave breaks out of the elapsed time. At 13,500 seconds and a 72-second takt, the plan is 187 units. Get takt from the takt time calculator.
What is a takt time clock?
It is a countdown that runs for one takt and then resets. Each station aims to finish as it reaches zero. It helps most on long-cycle lines, where the pace is hard to feel.
Is a takt board the same as an hour-by-hour board?
They overlap a lot. An hour-by-hour production board tracks plan and actual each hour, while a takt board puts takt on display and often updates per unit.
Can I build a takt board in Excel?
Yes, for a start. Enter takt and break times, calculate the plan from the clock, and type or import the actual count on a screen at the line. A part counting sensor can replace the typing later.
Fabrico is a light MES for OEE. It takes stops, speed and counts from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and operators tag the cause at the line.