OEE Gap Calculator
How far is your line from its target OEE, and where does the gap sit? Enter today's availability, performance and quality, or raw shift numbers, and a target. The calculator splits the gap by factor and turns each part into downtime minutes, speed loss minutes and scrap units to recover per shift. Updates as you type.
Your line, today and target
The defaults are the worked example below, not a benchmark. Replace them with your own numbers.
Where the gap sits, and what each factor must recover
Rows are rounded, so they can miss the total by 0.1.
Close the whole gap with one lever
The same gap, if only one factor moves and the other two stay as they are today.
Every route gives the same good units. What differs is how many minutes you must find, because a recovered downtime minute still runs at today's speed and scrap rate.
Which lever has the most room
Each factor today against a common rule-of-thumb level (Nakajima: 90% A, 95% P, 99.9% Q). The line marks that level.
The working
This is arithmetic on averages, not a forecast. It tells you how many minutes or units each factor must give back. It cannot tell you what that work costs, which stops cause the losses, or whether the line can sell the extra units.
The split between factors depends on the method you pick, so read the points as a guide, not a fact. The minutes and units are the solid part.
Get a second opinion on this result
Send it to the OEE Lab team. A Fabrico OEE specialist reads your numbers and gets back to you by email. To keep the result, use Copy link or Print above.
No newsletter, no spam. What you enter here, this result and its link go to the OEE Lab team. Privacy
A gap is only as real as the numbers under it.
Most gap sums start from a guessed OEE. Fabrico shows OEE per line and per shift from live data. Stops come from the PLC or IoT sensors, and the operator gives the cause. Where a machine has no usable signal, AI cameras count the output. So you can track each factor of the gap every shift.
Request a demoWhat the OEE gap calculator does
It answers one question: how far is the line from its target OEE, and how much of that distance sits in availability, performance and quality? Then it turns each share into something a team can act on: downtime minutes, speed loss minutes and scrap units per shift.
It works from today's OEE factors or from raw shift numbers. The target can be one OEE figure or a target per factor. With one figure, the plan closes the same share of each factor's loss, so the factor that loses most does the most work.
The other OEE Lab tools do different jobs. The OEE calculator gives you today's score. The six big losses calculator sorts lost minutes into loss types. The OEE loss tree simulator tests what-ifs on single losses. This page starts from the target and works backwards to the minutes.
The formulas
Gap (points) = target OEE - current OEE
With current factors A, P, Q and target factors A', P', Q', the gap in good minutes per shift is the gap × planned time. To split it by factor, the calculator offers two stated methods.
Loss tree order (default). Move one factor at a time, in the order time flows through the OEE loss tree:
- Availability part = (A' - A) × P × Q
- Performance part = A' × (P' - P) × Q
- Quality part = A' × P' × (Q' - Q)
The three parts add up exactly to the gap. The order can change the split a lot, especially when the gap is large or one factor moves far: a factor moved later is worked out at the improved levels of the ones before it, so it gets more points. Use log-share when you want a split that does not depend on the order.
Log-share. Each factor gets a share of the gap in proportion to the log of its own change:
Part of X = gap × ln(X' ÷ X) ÷ ln(target OEE ÷ current OEE)
Because ln(A'P'Q' ÷ APQ) = ln(A'÷A) + ln(P'÷P) + ln(Q'÷Q), the parts also add up to the gap, and the order does not matter. Two factors that improve by the same ratio get the same points.
The minutes to recover per shift are the same under both methods. They follow the loss tree order:
- Downtime minutes = (A' - A) × planned time
- Speed loss minutes = (P' - P) × A' × planned time, the extra net run time inside the new run time
- Scrap units = (Q' - Q) × total count at A' and P', where total count = planned time × A' × P' × ideal rate
For one lever on its own, the factor must reach target OEE ÷ (product of the other two). If that is above 100%, that lever cannot close the gap alone.
With one target OEE, the plan finds the share s of each factor's loss to close, so that (A + s(1 - A)) × (P + s(1 - P)) × (Q + s(1 - Q)) = target OEE.
Worked example: the default numbers
A packing line plans 450 minutes a shift and runs 10 shifts a week for 48 weeks. Today it reaches 80% availability, 80% performance and 95% quality. Its ideal rate is 20 units a minute, and each good unit carries a margin of 0.50. The target is 75% OEE.
Current OEE = 80% × 80% × 95% = 60.8%. The gap is 75.0 - 60.8 = 14.2 points, or 14.2% × 450 = 63.9 good minutes a shift.
To reach 75%, the plan closes 39.7% of each factor's loss. Availability goes from 80.0% to 87.9%, performance from 80.0% to 87.9% and quality from 95.0% to 97.0%.
| Factor | Today | Plan | Points | Recover / shift | Good min |
|---|---|---|---|---|---|
| Availability | 80.0% | 87.9% | 6.0 | 35.7 min downtime | 27.1 |
| Performance | 80.0% | 87.9% | 6.6 | 31.4 min speed loss | 29.8 |
| Quality | 95.0% | 97.0% | 1.5 | 138 scrap units (6.9 min) | 6.9 |
| OEE | 60.8% | 75.0% | 14.2 | 63.9 |
Why do equal moves in A and P give different points? In loss tree order, availability is moved first, at today's 80% performance. Performance is moved second, at the new 87.9% availability, so it gets slightly more. Log-share gives both the same 6.4 points.
Those 63.9 good minutes are 1,278 more good units a shift at 20 a minute. Over 480 shifts a year that is 613,440 units, worth 306,720 at a margin of 0.50, if the line can sell them.
With one lever alone: availability would need 75% ÷ (80% × 95%) = 98.7%, which is 84.1 minutes of downtime recovered a shift. Performance would need the same 98.7%, which is 67.3 minutes of speed loss recovered. Quality would need 117.2%, so it cannot close this gap alone.
How to pick the lever
Start with the factor that has the most room, not the one with the biggest number on the stop log. In the example, performance sits 15.0 points below the 95% rule-of-thumb level, availability 10.0 points below 90%, and quality only 4.9 points below 99.9%. Squeezing a factor that is already near its level usually costs more for each point.
Then look at what a recovered minute is worth. A downtime minute won back still runs at today's performance and quality, so it gives P × Q of a good minute: 0.76 here. A speed loss minute gives Q, 0.95. A quality minute gives a full minute. That is why the availability-only route needs 84.1 minutes and the performance-only route 67.3.
Those levels are a common rule of thumb, usually traced to Seiichi Nakajima's TPM work. They are not a benchmark for your process. A dedicated continuous line and a high-mix job shop sit in very different places; see the OEE benchmark report for published figures and their sources.
Last, price the work. Room tells you where points are available, not what they cost. A short changeover project and a new feeder can buy the same minutes for very different money. For a target per line that the team can own, Fabrico has a guide to setting OEE targets by line, and OEE Lab explains how to set OEE targets as a loss budget.
Common mistakes
- Subtracting factor gaps. The OEE gap is not (A' - A) + (P' - P) + (Q' - Q). OEE is a product, so the parts must be weighted, as in the formulas above.
- Treating every minute as equal. A downtime minute recovered gives less good output than a speed minute, because the recovered time still carries the other losses.
- Using the average cycle time as the ideal. It hides the speed loss, so performance looks close to 100% and the gap lands on the wrong factor. See performance over 100% if yours comes out too high.
- A target per factor that does not multiply out. 90% A, 90% P and 90% Q is 72.9% OEE, not 90%. The calculator shows the OEE your factor targets really give.
- Reading extra units as extra money. They earn margin only if you can sell them. With fixed demand, the gain shows up as fewer hours or less overtime.
OEE gap calculator FAQ
How do you calculate an OEE gap?
Gap in points = target OEE - current OEE. In the default example the line runs at 80% × 80% × 95% = 60.8% and the target is 75%, so the gap is 14.2 points. Times 450 planned minutes, that is 63.9 more minutes of good output at the ideal rate per shift.
How is the gap split between availability, performance and quality?
The default split follows the loss tree: first the availability change at today's performance and quality, then the performance change at the new availability, then the quality change at the new availability and performance. The three parts add up exactly to the gap. The log-share option splits it in proportion to ln(target factor ÷ current factor), which does not depend on the order.
Why does closing the gap by availability alone need more minutes?
A recovered minute of downtime still runs at today's performance and quality, so it gives only P × Q of a good minute. At 80% performance and 95% quality that is 0.76. A minute of speed loss recovered gives Q, and a minute of quality loss gives a full good minute.
What are typical ceilings for availability, performance and quality?
A common rule of thumb, usually traced to Seiichi Nakajima's TPM work, is 90% availability, 95% performance and 99.9% quality, for about 85% OEE. It is a rule of thumb, not a benchmark for your process. The calculator uses it only to show how much room each factor has left.
Should the target be split equally across the three factors?
Not always. With one target OEE, the calculator closes the same share of each factor's loss, so the factor with the biggest loss does the most work. If you know which losses you can remove, enter a target per factor instead and the split follows your plan.