Takt sets the target and balancing fills it. Calculate takt from demand, stack each operator's work on a yamazumi chart against the takt line, then move work until every operator sits just under it. Leave margin for stops: balancing right up to takt means any stop misses demand.
How takt and balancing fit together
Takt says how often the line must finish a unit, and balancing decides who does which work so that it can. Without takt you can even out a line and still miss demand.
This page is the method that joins the two. For takt on its own use the takt time calculator, and for the score of a finished balance use the line balancing calculator.
The six steps
Available time / demand, from the current plan.
Split every operation into elements, with work apart from walking and waiting.
One column per operator, with a line at takt.
Take out walking, searching and waiting first.
Shift elements from columns over the line into columns under it, in an order the product allows.
Compare the tallest column with takt, and allow for your real stops.
Step 1 and 2: the example line
Example: a hypothetical line has 450 available minutes, or 27,000 seconds, and demand of 360 units. Takt = 27,000 / 360 = 75 seconds.
Five operators work on it, and a stopwatch study gives these times per unit. The total is 355 seconds, with 292 of work and 63 of walking or waiting.
Step 3: the yamazumi
Yamazumi is Japanese for "stacked up". Each column stacks one operator's elements, so the chart shows at a glance who is over takt and who has room.
Operator D at 88 seconds sets the pace, so the line can make 27,000 / 88 = 306 units against a demand of 360. That is 54 short, even with no stops at all.
Yet the total work fits: 355 / 75 = 4.73, which rounds up to 5 operators. So the line has enough people, and the problem is how the work is shared.
Step 4: take out waste first
On a real line, walking and waiting come out before any work moves, or you just share the waste around. Here we leave the 63 seconds in for now, so that you can see further down what they cost.
Step 5: move work to the takt line
Example: in the order the product allows, B passes 8 seconds to A and 1 to C, while D passes 12 seconds to C and 4 to E.
| Operator | Before | Change | After |
|---|---|---|---|
| A | 62 | +8 | 70 |
| B | 81 | -9 | 72 |
| C | 58 | +13 | 71 |
| D | 88 | -16 | 72 |
| E | 66 | +4 | 70 |
| Total | 355 | 0 | 355 |
Now the line can make 27,000 / 72 = 375 units, and balance efficiency rises from 355 / (5 x 88) = 80.7% to 355 / (5 x 72) = 98.6%.
Those scores count the whole 355 seconds, walking and waiting included. On the 292 seconds of real work alone, the result is 292 / (5 x 72) = 81.1%, which is why 98.6% is not a finished job.
Step 6: the margin takt does not show you
Takt assumes the line runs every available second. A column at 72 seconds against a takt of 75 leaves room for only 4% of lost time, because 72 / 75 = 96%.
That is 18 minutes in a 450-minute shift, for every stop, slow cycle and reject together. The ratio is the OEE the line needs just to meet demand, and OEE for assembly lines covers it from the OEE side.
So many plants balance to a shorter target, called operational takt or planned cycle time. Example: if this line loses 10% of its time on a normal shift, the target is 75 x 0.90 = 67.5 seconds.
Add a person, or take out waste?
Against 67.5 seconds, the 355 seconds need 355 / 67.5 = 5.26, so a sixth operator. Balance efficiency against takt then falls to 355 / (6 x 75) = 78.9%.
Now use the grey caps on the chart instead. Remove half of the 63 seconds of walking and waiting, and the total falls to 323.5 seconds, or 4.79 operators, so five people can each hold about 64.7 seconds.
That is why step 4 comes before step 5. See the 8 wastes of lean for what to look for, and how to increase production capacity for other options.
When takt changes
A balance holds for one takt only. If demand rises to 400 units, takt becomes 67.5 seconds, and this same line needs its margin all over again.
Keep the elements and their times in one sheet, so a new balance is desk work and not a new study. On a line that builds several products, start from the mixed-model takt time calculator.
How to keep it on the floor
- Write down the new work. A balance that lives only on the chart soon drifts back, so update the work instructions.
- Post takt at the line. A takt time board lets the crew see the pace it was balanced to.
- Re-time the tallest column monthly. If it has grown, find out why before you move anything.
- Train across stations. A move on paper fails if nobody has been trained on the new element.
Why balances fall apart
- Balancing to exactly takt. Any stop then costs units you cannot get back.
- Using average times. A column that averages 70 but swings up to 85 still misses takt, so look at cycle time variation too.
- Fixing only the tallest column. The next column often becomes the bottleneck straight away.
- Ignoring machine time. On a station with a machine, count the time the person really has to be there, as cycle time vs touch time explains.
The margin in a balance depends on the OEE the line really reaches. Fabrico is a light MES for OEE that shows OEE per line and shift, from stops, speed and counts taken live at the line. See how Fabrico works as a light MES.
What people ask next
How does takt time relate to line balancing?
Takt is the target each station must meet, and balancing shares out the work so that it does. Balancing without takt evens out the line but may still miss demand. Calculate takt first with the takt time calculator.
What is a yamazumi chart with takt time?
It is a stacked column chart with one column per operator and a line drawn at takt. Each column stacks that operator's work elements, so anything above the line cannot meet demand.
How many operators do I need from takt time?
Divide total work content by takt and round up. Here 355 / 75 = 4.73, so five operators, if the work can be shared evenly. Check the result on the line balancing calculator.
What is the difference between takt and operational takt?
Takt comes from demand only. Operational takt, also called planned cycle time, is shorter because it leaves room for normal losses. If you lose 10%, a 75-second takt becomes a 67.5-second target.
Should every station be balanced to exactly takt?
No. With no margin, any stop or slow cycle costs units the line cannot recover. Balance to a target under takt, based on what your line really loses, which how to track downtime helps you measure.