Short answer

Cycle time is how often a unit comes out of a step. Touch time is the part of that time someone is really working on the unit. Example: a 60-second bench cycle with 44 seconds of touch time spends 16 seconds on walking and waiting, and that gap is usually cheaper to win back than faster hands.

Two clocks at one bench

Watch an operator for one cycle. The cycle time is the gap between two finished units, and the touch time is what is left after you take out walking, reaching for parts and waiting.

Touch time measures how much of the cycle holds real contact with the product. So the two together show how much of the pace is work, and how much is not.

Which definition of touch time?

Plants use the term in two ways, and the difference is large on a machine. Our definition is hands-on time: a person working on the unit.

The common alternative counts any work on the unit, including time when a machine cuts it unattended. Some people then call this process time, as cycle time vs process time explains.

Touch time is also not the same as value-added time. Inspecting or redoing a unit is touching it, though it adds nothing the customer pays for.

The ratio below assumes one person on the unit. With two people working at once, their hands-on time adds up and can pass the cycle time, so compare per person there.

Example 1: a manual bench

Example: a hypothetical assembly bench is timed with a stopwatch over five cycles. Each row splits the cycle into touch time and everything else.

CycleCycle timeTouch timeThe rest
158 s43 s15 s
261 s45 s16 s
360 s44 s16 s
463 s46 s17 s
558 s42 s16 s
Average60 s44 s16 s
Five cycles are enough to show the idea. Use more for a real study, on the cycle time calculator.

The touch ratio is 44 / 60 = 73.3%. The remaining 16 seconds split into 9 of walking and reaching, and 7 of waiting for the next part.

Touch time44 s
Walking and reaching9 s
Waiting for the next part7 s
The average cycle laid out in order. Each bar starts where the last one ended.

Take the 9 seconds of walking out by moving the parts bin closer, and the bench's own time falls to 51 seconds with the touch time unchanged. Output can then rise from 60 to 70.6 units an hour, but only if parts arrive when the bench needs them.

The waiting is a different case. It may come from a blocked or starved station next door, and while a neighbor sets the pace, the saved 9 seconds just become more waiting.

Example 2: a CNC machine

Machines pull the two apart much further. Example: an operator loads a part for 25 seconds, the machine cuts for 150 seconds unattended, and the operator unloads for 15 seconds.

Operator: load 25 s, unload 15 s Machine: cuts 150 s Cycle time 190 s
The operator is needed for 40 of the 190 seconds. The remaining 150 are free for other work.

The cycle time is 190 seconds, or about 19 parts an hour. Touch time on our definition is 40 seconds, and on the wider definition it is 190.

The gap tells you how many machines one person can run. Add 10 seconds to walk between machines, and one operator needs 50 seconds a part, so 190 / 50 = 3.8, which means 3 machines.

Set-upParts per hourLabor time per part
1 operator, 1 machine3,600 / 190 = 18.9190 s
1 operator, 3 machines3 x 3,600 / 190 = 56.863 s
Cycle time per machine did not change. What changed is how much of the person's time each part uses.

This is why labor figures such as units per labor hour depend on touch time, while output depends on cycle time. Line-balancing also has to use a person's time here, as takt time and line balancing shows.

Across a whole process

The same comparison works on a whole route, and the numbers get much smaller. Example: a unit gets 18 minutes of total touch time in a route with a 12-hour throughput time, so the ratio is 18 / 720 = 2.5%.

Few improvements will come from faster hands at that point, so go after the waits instead. A value stream map shows them step by step.

How to measure touch time

  1. Film 10 or more cycles. With consent, video lets you re-watch and split elements, and it beats a hurried stopwatch.
  2. Define touch up front. Decide whether handling, inspection and tool changes count, and write it down.
  3. Split the rest. Put walking, reaching, waiting and rework in their own columns, because each has a different fix.
  4. Measure the normal case. Use a trained operator at a steady pace, on the usual product.
  5. Compare with cycle time from the count. Run time / units made shows what the shift really delivers, including micro-stops.

Where touch time studies mislead

  • Using touch time to plan output. Output follows cycle time, so a plan built on 44 seconds on a 60-second bench will be short every day.
  • Pushing people to touch faster. The 16 seconds outside touch time are usually cheaper to remove, and safer too.
  • Treating touch as value-added. Rework and repeat checks are touch time, and they are also waste. See the 8 wastes of lean.
  • Mixing the two definitions. A report showing 40 seconds one month and 190 the next may just have changed definition.
  • Using the study as a scorecard. People change how they work when they feel judged, and the data suffers.
See it live in Fabrico

A stopwatch study shows one morning at one bench. Where cameras are fitted, the video of any stop can be streamed on request next to its machine data, on every shift. See how Fabrico uses cameras on the line.

What people ask next

What is touch time in manufacturing?

It is the time someone is really working on the unit, leaving out walking, reaching and waiting. Some plants also count unattended machine time as touch time, so write down your definition.

What is the difference between cycle time and touch time?

Cycle time is how often a unit comes out of a step, and touch time is the hands-on part of that. A 60-second cycle may hold 44 seconds of touch time. See the cycle time calculator.

Is touch time the same as value-added time?

No. Touch time includes everything done to the unit, including inspection and rework. Value-added time is only the work the customer would pay for, so it is usually shorter.

What is a good touch time ratio?

We found no neutral benchmark, because it depends so much on the process. Track the ratio at each station over time, and go after the largest item in the rest. A machine-paced step will have a lower ratio by design.

How does touch time help with line balancing?

On manual stations it shows how much real work has to be shared out, apart from waste you should remove first. On machine stations it shows how much of an operator's time each machine takes. See takt time and line balancing.

See OEE per line and shift on your own machines

Fabrico is a light MES for OEE. It takes stops, speed and counts from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and operators tag the cause at the line.

Book a Fabrico demo

← More OEE Lab guides · Open the cycle time calculator →

OEE essentials: OEE calculator · What is OEE · Six big losses · Availability · TEEP · Cost of downtime · OEE benchmark · Free OEE tracker · Free OEE software · How to track downtime · How to implement OEE · Light MES vs full MES