Time and products
Use one shift or one day, and keep time and demand on the same period.
By product
A repeating build sequence
Want a second look at this result?
Leave your work email if you would like the OEE Lab team to get in touch about your numbers. To keep the result, use Copy link or Print above.
No newsletter, no spam.
The mix works on paper when the line runs at its cycle.
Stops and slow running eat the spare minutes first. Fabrico, a light MES for OEE, takes stops, speed and counts live from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and shows OEE per line and shift.
Request a demo Contact usHow to calculate takt time for multiple products
A mixed model line has one takt time, whatever the product. You divide the available time by the total demand of all products added together.
The line keeps up when the load is at or under 100%. That is the same as saying the work for all products fits inside the available time.
For one product, the takt time calculator is all you need. This page adds the mix.
Example: three models on one line
Example: a line with 450 available minutes builds 300 of Model A at 46 seconds, 150 of Model B at 60 seconds and 50 of Model C at 72 seconds.
| Product | Demand | Cycle | Work, s | Against takt |
|---|---|---|---|---|
| Model A | 300 | 46 s | 13,800 | -8 s |
| Model B | 150 | 60 s | 9,000 | +6 s |
| Model C | 50 | 72 s | 3,600 | +18 s |
| Total | 500 | 52.8 s | 26,400 | -1.2 s |
Common takt = 450 × 60 ÷ 500 = 54 seconds. Weighted cycle = 26,400 ÷ 500 = 52.8 seconds.
Line load = 52.8 ÷ 54 = 97.8%. That leaves 600 seconds, or 10 minutes, in the whole shift.
Why the simple average misleads
The plain average of 46, 60 and 72 is 59.3 seconds, which is over the 54 second takt. On that number you would add a shift you do not need.
The reverse also happens. If the slow product is the one in high demand, a plain average says you are fine while the line falls behind.
What the line load means
- Load under about 85%: room for stops and variation, though OEE losses still count against it.
- Load between 85% and 100%: the mix fits only if the line runs close to its cycle. Treat it as tight.
- Load over 100%: the mix does not fit. Cut cycle time on the heavy products, add time or add a parallel station.
The load also tells you the OEE you need, if your cycle times are ideal cycles. At a 97.8% load the line needs at least 97.8% OEE to hold, so plan some extra time.
The guide to OEE with mixed products shows how to measure it.
The build sequence
The tool also gives a repeating pattern that spreads each product through the run. It uses the smallest repeat that matches your demand, so 300, 150 and 50 become 6, 3 and 1 in every 10 units.
Spreading the slow models stops them from bunching. Two Model C units in a row would each overrun takt by 18 seconds, and the stations behind them would feel it.
The sequence is a starting point. Real lines also weigh changeover time, which the changeover cost calculator can price.
Mixed model takt errors
- A separate takt per product. Dividing the shift by Model C's 50 units gives 540 seconds, a pace that means nothing on a shared line.
- Using total cycle instead of the slowest station. For each product, enter the cycle at its slowest station. A cycle time study finds that number.
- Taking unplanned downtime off the available time. Takt comes from planned time. Losses show up as the gap you have to close, as takt, cycle and lead time explains.
- Leaving out changeovers. If products change in batches, take the planned changeover minutes off the available time first.
- Keeping an old mix. When the mix moves, the load moves, even if total demand stays the same.
Mixed model questions
How do you calculate takt time for multiple products?
Add up the demand for all products and divide the available time by that total. With 450 minutes and 500 units, the common takt is 54 seconds, whatever the product.
What is a weighted cycle time?
It is the average cycle time per unit, with each product counted by its demand. Multiply each cycle by its demand, add the results and divide by total demand.
Can a product have a cycle time above takt on a mixed model line?
Yes, as long as the weighted cycle stays at or under takt and the slow units are spread out. A faster product makes up the time, but a run of slow units will still put stations behind.
What does a line load over 100% mean?
The work for the mix takes longer than the available time, so the line cannot make all the demand. You need less cycle time on the heavy products, more hours or another station, and the line balancing calculator is a good next step.
Does this calculator include OEE losses?
No. It compares demand with the planned cycle, so a load of 90% means the line needs at least 90% OEE if those cycles are ideal cycles. Check your real figure with the OEE calculator.