OEE Lab / Tools / Shift Pattern Calculator

Shift Pattern Calculator

Compare seven shift patterns side by side for one line. See the planned production time, the good units a week at your OEE, the crews you need and the OEE each pattern needs to meet demand. Updates as you type.

Your line and your week

Time lost per shift, your OEE, the ideal rate and the weekly demand. The defaults are the worked example below.

Time off the line, per shift
min
Scaled to shift length: a 12 h shift gets 1.5 times this.
If it keeps running, breaks stay inside planned production time.
min
Meetings, cleaning.
min
Line stopped at shift change. Skipped with one shift a day.
Line and demand
%
Measured, not the target.
Good units you must ship.
The fastest proven speed, the same one your OEE uses.
Your own pattern
Defaults: 95,000 units a week at 65% OEE
Smallest pattern that meets demand
-
Fewest planned hours that make the weekly demand at your OEE
Planned time / week
-
Good units / week
-
OEE needed
-
Loading
-
Crews
-
Hours / operator
-

Seven patterns side by side

Calendar time is 168 hours a week for every pattern. The bar under planned time shows loading, its share of those 168 hours.

PatternScheduled h / weekPlanned h / weekGood units / weekOEE neededCrewsh / operator

OEE needed above 85% is flagged as unrealistic and above 100% as impossible. Hours per operator is scheduled crew hours divided by crews, paid breaks included, before holidays, sickness and training.

One OEE for every pattern is a simplification. Nights, 12 hour shifts and Saturday crews often run at a different OEE, and more output can mean more changeovers. Labour cost, premiums and local working time rules are not in these numbers. Use the result to shortlist patterns, then test the shortlist with your own shift data.

The working, with your numbers

    Get a second opinion on this result

    Send it to the OEE Lab team. A Fabrico OEE specialist reads your numbers and gets back to you by email. To keep the result, use Copy link or Print above.

    Sent. A Fabrico OEE specialist will read your numbers and get back to you by email.

    No newsletter, no spam. What you enter here, this result and its link go to the OEE Lab team. Privacy

    A new pattern only pays if every shift runs well.

    The same line rarely runs the same on days, nights and weekends. Fabrico shows OEE per line and per shift. Stops come live from the PLC or IoT sensors and the operator gives the cause, and AI cameras count output where a machine has no usable signal.

    See OEE per line and shift in your own plant: book a demo with a Fabrico consultant.

    Request a demo
    Our tools stay free either way.

    What the shift pattern calculator does

    It takes one line and asks a simple question for seven shift patterns: how many planned hours does each one give you, and is that enough to make your weekly demand at the OEE you run today?

    Six patterns are fixed: one, two and three 8 hour shifts on 5 days, three shifts with Saturday overtime, 12 hour continuous with 4 crews, and 8 hour continuous with 5 crews. The seventh is yours to set.

    For each pattern you get the planned production time, the loading, the good units a week, the OEE needed to meet demand, the crews and the average weekly hours per operator. The readout names the smallest pattern that meets demand, which is the one with the fewest planned hours.

    The formulas

    The calculator uses the same time model as the OEE loss tree simulator, after Overall Equipment Effectiveness (R. C. Hansen, 2001). Calendar time is all 168 hours of the week. Planned production time is the part you plan to run.

    Good units = planned production time × ideal rate × OEE

    • Scheduled time = shifts a day × hours a shift × days a week.
    • Planned production time per shift = shift length - breaks (if the line stops) - planned stops - handover. Breaks are scaled to shift length.
    • Planned production time per week = planned time per shift × shifts a week.
    • Loading = planned production time ÷ calendar time (168 h). It is the U in TEEP = OEE × U.
    • OEE needed = weekly demand ÷ (planned production time × ideal rate).
    • Hours per operator = scheduled crew hours ÷ crews.

    Your OEE carries planned production time down to fully productive time. Downtime takes it to operating time, which the simulator calls run time, then speed loss and quality loss take it the rest of the way. Fabrico explains the first step in planned production time vs operating time.

    Worked example: the default numbers

    Example: a line runs at 65% OEE with an ideal rate of 1,200 units an hour and must ship 95,000 good units a week. Each 8 hour shift loses 30 minutes to breaks (the line stops), 15 minutes to a meeting and cleaning, and 10 minutes to handover. The single day shift has no shift change, so it skips the handover.

    That leaves 480 - 30 - 15 - 10 = 425 planned minutes in an 8 hour shift. A 12 hour shift gets 45 minutes of breaks, so it keeps 720 - 45 - 15 - 10 = 650 minutes.

    PatternPlanned h / weekGood units / weekOEE needed
    1 × 8 h, 5 days36.328,275218.4%
    2 × 8 h, 5 days70.855,250111.8%
    3 × 8 h, 5 days106.382,87574.5%
    3 × 8 h, 6 days127.599,45062.1%
    2 × 12 h, 7 days151.7118,30052.2%
    3 × 8 h, 7 days148.8116,02553.2%
    Own: 2 × 10 h, 6 days107.583,85073.6%

    Take 3 × 8 h on 6 days: 425 minutes × 18 shifts = 7,650 minutes, or 127.5 hours. At 1,200 units an hour that is 153,000 units at 100% OEE, and 99,450 good units at 65%. The OEE needed is 95,000 ÷ 153,000 = 62.1%, so it meets demand with 4,450 units to spare. Loading is 127.5 ÷ 168 = 75.9%, and TEEP is 65% × 75.9% = 49.3%.

    Three shifts on 5 days falls short by 12,125 units. It would need 74.5% OEE, nearly 10 points above today. So Saturday overtime is the smallest pattern that works, but it puts each of the 3 crews on 48 hours a week. That is fine as a bridge, and hard to hold for months.

    Note the two continuous patterns. 2 × 12 h keeps 2.9 more planned hours a week than 3 × 8 h, because it has 14 handovers a week instead of 21, even after the longer breaks.

    How to choose a pattern

    Start with the smallest pattern that meets demand at your real OEE, then ask what each step up costs in people and fatigue. A few practical points:

    • 12 hour shifts give more planned time, not always more output. Fatigue builds in the last hours of a long shift, and more so on nights. Compare crews over a full rotation before you judge; see OEE on 12 hour shifts.
    • Every handover costs twice. The minutes at the change are only part of it. Start-up after a handover is often slow too; see first hour of shift losses and end of shift losses. Fewer, longer shifts mean fewer of both.
    • Your OEE will not be the same on every shift. Nights and weekend crews often have less support on hand. Measure each shift before you plan on one number; see why OEE differs between shifts.
    • Raise OEE before you add a shift. In the example, 74.5% OEE on 3 shifts does the job of Saturday overtime. Use the loss tree simulator to see where those points could come from.
    • Check loading against TEEP. A continuous pattern lifts loading close to 90% in the example. The TEEP calculator shows how much capacity is left.

    Common mistakes

    • Planning on the OEE target. Use the OEE you measured over recent weeks. A pattern that needs your target OEE has no margin.
    • Counting handover twice. If your OEE already counts handover as downtime, set handover to zero here.
    • Leaving breaks in when the line stops. If nobody covers the break, it is not planned production time. See how to count breaks in OEE.
    • Using the average rate as the ideal. The average already contains speed loss, so good units come out too low and the OEE needed too high.
    • Reading hours per operator as a roster. It is an average before holidays, sickness and training. A real roster needs cover on top.

    Shift pattern calculator FAQ

    Which shift pattern gives the most production time?

    A continuous pattern, because it schedules all 168 hours of the week. Between the two continuous patterns, 2 × 12 hours usually keeps a little more planned time than 3 × 8 hours, because it has two handovers a day instead of three. In the default example that is 151.7 against 148.8 planned hours a week.

    How many crews does a 12 hour continuous pattern need?

    Four. Two 12 hour shifts a day for 7 days is 168 crew hours a week, so four crews average 42 hours each. Patterns like 2-2-3 and DuPont are different ways to rotate those four crews.

    Do breaks come off planned production time?

    If the line stops for the break as planned, yes: the break is not planned production time and does not lower OEE. If a relief crew keeps the line running, the minutes stay in. Set the line stops for breaks switch to match your plant.

    What OEE should I plan a shift pattern on?

    Your measured OEE over recent weeks, not a target. The calculator flags any pattern that needs more than 85% OEE as unrealistic, because 85% is the world-class figure usually traced to Seiichi Nakajima's Introduction to TPM (1988).

    What is loading, and how does it relate to TEEP?

    Loading is planned production time divided by calendar time, the 168 hours of a week. TEEP is OEE times loading. A pattern with more loading raises TEEP even if OEE stays the same.

    Should shift handover count as a planned stop?

    Count it once. This calculator takes handover out of planned production time. If your OEE already counts handover as downtime, set handover to zero here, or the same minutes are lost twice.