Machine Hour Rate Calculator, with OEE
Build the hourly rate of one machine from what it costs to own and to run. Then see what one hour of good output really costs at your OEE, and how far that falls at a target OEE. Use it for costing and quoting. Updates as you type.
Your machine, one year
The defaults are an example machine, not a benchmark. Replace them with your own numbers.
How the rate falls at a target OEE
Same machine, same costs, same planned hours. Only the share of hours that turn into good output changes.
Where the hourly rate comes from
Rows are rounded, so they can miss the total by a cent.
The working
This is a costing estimate, not your accounts. How you spread costs changes the rate: the hours base, the interest rate, what counts as fixed maintenance, how much floor space you charge. Two honest people can get two different rates for the same machine.
Power, tooling and wear are charged on run hours: planned hours × the availability you enter. Fixed costs and the operator are charged on every planned hour. Use the result to quote and to compare, and check it with your finance team.
Get a second opinion on this result
Send it to the OEE Lab team. A Fabrico OEE specialist reads your numbers and gets back to you by email. To keep the result, use Copy link or Print above.
No newsletter, no spam. What you enter here, this result and its link go to the OEE Lab team. Privacy
A machine rate is only as good as the OEE behind it.
Most costing sheets assume an OEE. Fabrico measures it. It records stops live from the PLC or IoT sensors, and the operator gives the cause. Where a machine has no usable signal, AI cameras count the output. You get the real productive hours of each line, per shift, so the rate you quote rests on fact, not on a guess.
Request a demoWhat a machine hour rate is
A machine hour rate is the cost of running one machine for one hour. Cost accountants use it to charge machine costs to products. Job shops use it to quote: hours on the machine × the rate.
It has two parts. Fixed costs come with owning the machine, whether it runs or not: depreciation, interest on the money tied up in it, the floor it stands on, insurance and fixed maintenance. Running costs come with each hour it runs: power, consumables and tooling, and wear.
This page is not the same as the other cost tools on OEE Lab. The cost per unit guide takes a period's total cost and divides it by good units. The downtime cost calculator prices an hour of stopped line. This tool builds the hourly rate of one machine from its parts, for costing and quoting.
A machine hour rate is a traditional way to spread overhead. If you want to compare it with other methods, Fabrico has a guide on activity-based costing vs traditional costing.
The formulas
Rate per planned hour = fixed costs per year ÷ planned hours + running costs per run hour × availability + operator cost per hour
- Depreciation = (purchase price - residual value) ÷ life in years. Straight line.
- Interest on capital = (purchase price + residual value) ÷ 2 × interest rate. The average capital tied up over the machine's life.
- Floor space = m² × cost per m² per year.
- Insurance and fixed maintenance: the yearly amounts.
- Planned hours = shifts per day × hours per shift × days per week × weeks per year.
- Power per hour = kW × load factor × price per kWh.
- Running costs per run hour = power + consumables and tooling + variable maintenance.
- Run hours = planned hours × availability. The machine only draws power and wears tools while it runs, so running costs are charged on these hours.
- Operator cost per hour = operators per machine × cost per operator, if you include labour. It is charged on every planned hour, because people are paid while the machine stands.
Then rate per planned hour = total cost per year ÷ planned hours.
Then the OEE step. Only part of the planned hours turn into good output at the ideal rate. That part is fully productive time.
Rate per productive hour = total cost per year ÷ (planned hours × OEE)
That is the same as the rate per planned hour ÷ OEE. OEE is always at or below availability, because OEE = availability × performance × quality.
Cost per good unit = rate per productive hour ÷ ideal rate
The ideal rate is the fastest proven rate for the part; see ideal run rate. The cost per good unit here is machine cost only. Material is not in it.
Worked example: the default numbers
The defaults are an example, not a benchmark. A CNC machine costs 250,000 and is worth 25,000 after 10 years. Money costs 5% a year. It takes 30 m² at 120 a m² a year. Insurance is 2,500 and fixed maintenance 6,000 a year.
It draws 30 kW at a 60% load, at 0.18 a kWh. Tooling and consumables cost 4.00 an hour and wear another 2.50. It is planned for 2 shifts of 7.5 hours, 5 days a week, 46 weeks a year, and runs 85% of that time. Labour is costed apart.
| Component | Working | Per year | Per planned hour |
|---|---|---|---|
| Depreciation | (250,000 - 25,000) ÷ 10 | 22,500 | 6.52 |
| Interest | (250,000 + 25,000) ÷ 2 × 5% | 6,875 | 1.99 |
| Floor space | 30 × 120 | 3,600 | 1.04 |
| Insurance | given | 2,500 | 0.72 |
| Fixed maintenance | given | 6,000 | 1.74 |
| Fixed costs | sum | 41,475 | 12.02 |
| Power | 30 × 60% × 0.18 = 3.24 × 2,932.5 h | 9,501 | 2.75 |
| Consumables, tooling | 4.00 × 2,932.5 h | 11,730 | 3.40 |
| Variable maintenance | 2.50 × 2,932.5 h | 7,331 | 2.13 |
| Total | 41,475 + 9.74 × 2,932.5 | 70,038 | 20.30 |
So the machine hour rate is 20.30 per planned hour: 12.02 of fixed cost and 9.74 × 85% = 8.28 of running cost. Depreciation is the biggest part, at about 32% of the cost.
Now the OEE step. At 60% OEE, 3,450 × 60% = 2,070 hours make good output at the ideal rate. The same 70,038 spread over 2,070 hours is 33.83 per productive hour. At an ideal rate of 40 units an hour, each good unit carries 33.83 ÷ 40 = 0.85 of machine cost.
At a target of 75% OEE, the same year of cost spreads over 2,587.5 productive hours. The rate per productive hour falls to 27.07, and the cost per good unit to 0.68. That is 20% less per good unit, from the same machine. The example keeps availability at 85%, so the gain comes from speed and quality.
If you include an operator at 32 an hour, minding two machines (0.5 per machine), the rate rises by 16.00 to 36.30 per planned hour, and 60.50 per productive hour at 60% OEE.
Planned hours or productive hours: which to quote on
Quote hours and rate on the same base. That is the whole rule. The mistake is to mix them.
Planned-hour rate with planned hours. If your quote estimates the hours a job will hold the machine, stops, slow cycles and scrap included, use the planned-hour rate. The losses are already in the hours.
Productive-hour rate with ideal hours. If your quote takes cycle time × quantity, the hours are ideal hours. They assume no stops, full speed and no scrap. Multiply them by the planned-hour rate and you under-quote by the full OEE gap. Use the productive-hour rate instead.
Most quotes start from cycle times. So the productive-hour rate is often the honest one. It also shows what OEE is worth in money: every point of OEE lowers the cost of a good hour. For the capacity side of the same idea, see the TEEP calculator and the machine utilization calculator.
Common mistakes
- Using 8,760 hours as the base. A machine that runs two shifts gets a rate that is far too low. Use the hours you plan to run.
- Quoting ideal hours at the planned-hour rate. Cycle time × quantity leaves out every loss. Use the productive-hour rate, or add the losses to the hours.
- Counting the operator twice. If the rate includes labour, take labour out of the quote's other lines, and the other way round.
- Assuming an OEE you have never measured. A guessed 85% makes every quote look cheap. Measure it on the machine, or use the OEE calculator on a real shift.
- Leaving the rate alone for years. Energy prices, shifts and OEE change. Rebuild the rate at least once a year.
Machine hour rate FAQ
What is a machine hour rate?
It is the cost of running one machine for one hour. You add up the fixed costs of owning the machine for a year and divide them by the hours you plan to run it, then add the costs that come with each running hour, such as power and tooling.
How do you calculate a machine hour rate?
Machine hour rate = fixed costs per year ÷ planned hours per year + running costs per run hour × availability. Fixed costs are depreciation, interest on capital, floor space, insurance and fixed maintenance. Running costs are power, consumables and tooling, and variable maintenance, charged only on the hours the machine runs.
Should the machine hour rate include the operator?
It depends on how you cost. Many job shops quote one rate with the operator in it. Others keep labour as its own line. Pick one way and use it everywhere, so labour is never counted twice or left out.
Why divide by productive hours instead of planned hours?
Because a customer only pays for good parts. If the machine reaches 60% OEE, only 60% of the planned hours turn into good output at the ideal rate. The full year of cost has to be carried by those hours, so each one costs the planned rate ÷ OEE.
Which hours should I use as the base?
Use the hours you really plan to run the machine in a normal year: shifts × hours per shift × days × weeks, with planned breaks taken out. Do not use 8,760 calendar hours unless the machine truly runs around the clock.
Does a higher OEE lower the machine hour rate?
The rate per planned hour stays the same, because the costs and the planned hours do not change. The rate per productive hour falls, because the same costs are spread over more good-output hours. That is the number that sets your cost per good part.