Unplanned downtime is any stop inside planned production time that was not on the schedule. Examples: a motor fails, a labeller jams, cartons run out, the operator loads the wrong recipe, a batch fails a test, a changeover runs past its standard time. The test is one question: was this stop on the schedule before the shift began?
Examples by type
Teams often picture a breakdown when they hear "unplanned". The list is wider than that, and only the first group is about broken equipment.
The equipment failed
- A motor bearing seizes on a conveyor.
- A drive trips on overcurrent and will not reset.
- A photo eye gives false readings because of dust.
- A hydraulic hose bursts on a press.
Someone or some procedure caused it
- The operator loads the wrong recipe, and the run stops for a reset.
- A wrong label roll goes on after a changeover.
- A machine is set outside its window, then starts to jam.
Something from outside stopped the machine
- Cartons do not arrive at the line. See waiting for material.
- Nobody is free to run the station. See waiting for an operator.
- The palletizer stops, and the filler is blocked behind it. See upstream and downstream stops.
- Compressed air pressure falls, or the site loses power.
Quality stopped the run
- A lab result holds the line until someone releases the batch.
- Raw material arrives out of spec, and the process will not run.
- Extra tests are ordered after a customer complaint.
One shift, stop by stop
Example: a packaging line runs 06:00 to 14:00, which is 480 minutes. The crew breaks for 30 minutes and nobody relieves them, so this plant leaves that out and plans 450 minutes.
| Time | What happened | Min | Class |
|---|---|---|---|
| 06:20 | Sensor fault at startup | 12 | Unplanned, technical |
| 07:10 | Changeover, to standard | 30 | Planned |
| 08:05 | No cartons at the line | 18 | Unplanned, induced |
| 09:30 | Break, no relief | 30 | Excluded |
| 10:25 | Drive trip on the filler | 35 | Unplanned, technical |
| 11:40 | Wrong label roll | 9 | Unplanned, operational |
| 12:30 | Cleaning, 15 planned, 21 taken | 15 + 6 | Planned + unplanned |
| 13:20 | Quality hold on a batch | 14 | Unplanned, quality |
Unplanned minutes are 12 + 18 + 35 + 9 + 6 + 14 = 94. That is 94 / 450 = 20.9% of planned time.
Planned stops are 30 + 15 = 45 minutes, so run time is 450 - 94 - 45 = 311 minutes. Availability is 311 / 450 = 69.1%.
Technical faults explain only 47 of the 94 unplanned minutes, so a team that watches breakdowns alone would see half the problem. The full method is on the unplanned downtime formula page.
Gray areas: which way do they go?
These cases cause most of the arguments. Agree on them once and write the answers on the log sheet.
| Situation | Usual class | Why |
|---|---|---|
| Maintenance decided the morning of the shift | Unplanned | It was not on the schedule beforehand |
| Changeover runs past its standard | Split | The standard part is planned, and the rest is not |
| Extra clean after a spill | Unplanned | A routine clean is planned, but this one is not |
| Power cut at the site | Unplanned | It was outside the plant's control, but it still cost planned time |
| Line idle, no orders | Excluded | The line was not planned to run |
| Jam cleared in 40 seconds | Short stop | Below the threshold, it falls in performance |
| Line running slower than ideal | Not downtime | The machine is running, so it counts as a speed loss |
For the last two rows, see minor stops vs breakdowns and speed losses. The broader definitions are on planned vs unplanned downtime.
Examples by machine type
The same class looks different in each process. These are typical of what appears on a stop log, not a ranking.
- Bottling or canning line: a capper fault, a bottle tip at the labeller, a held batch, a blocked outfeed. See food and beverage.
- CNC machine: a broken tool, a probe alarm, a wait for a first-off check. See OEE for CNC machines.
- Injection moulding: a stuck part, a mould temperature fault, wet resin that fails. See OEE for injection moulding.
- Packaging: a glue fault on a case packer, a film break on a wrapper. See OEE and downtime in packaging.
Use these examples to train the crew
Definitions on a slide rarely survive the first night shift. Examples from your own line do.
- Take ten stops from last week and classify them with each crew.
- Where two people disagree, write the answer on the log sheet.
- Replace the examples above with your own machine names and faults.
- Repeat it when a new product or machine arrives, since new stops bring new arguments.
Once crews agree, the unplanned figure can be compared from week to week. Without that, a change in the number may only mean a different person filled in the log.
The rules for a log that crews keep up are on operator downtime logging.
How these examples hit OEE
Every example above, once over the threshold, comes off availability in the same way. So 45 minutes of no cartons costs as much OEE as 45 minutes of a failed motor.
The cost can differ, though, since a failure may also bring parts, overtime and scrap at restart. For the wider view, read the cost of downtime.
The first step for any of them is the same: log each stop with a time and a reason. Then rank them, as in how to reduce unplanned downtime.
A log like the one above takes discipline to keep by hand. Fabrico takes stops, speed and counts live from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and operators tag the cause at the line. See Fabrico, a light MES for OEE.
What people ask next
What is an example of unplanned downtime?
A conveyor motor that fails during a run is the classic case. Running out of cartons and waiting on a held batch are also unplanned. See machine downtime reasons for a fuller list.
Is a changeover unplanned downtime?
A changeover within its planned time is planned, though it still lowers availability. Any time past the standard counts as unplanned. See how to count changeovers in OEE.
Is preventive maintenance ever unplanned downtime?
If it was on the schedule before the shift, it is planned. If it was decided that morning because something looked wrong, treat it as unplanned. See does maintenance count in OEE.
What is the difference between planned and unplanned downtime?
Planned stops were on the schedule, and unplanned ones were not. Both lower availability when they fall inside planned production time. The full comparison is on planned vs unplanned downtime.
How do I calculate how much unplanned downtime I have?
Divide unplanned stop minutes by planned production minutes and multiply by 100. The unplanned downtime formula page has a full example.