How to Calculate Downtime Percentage: Formula

OL By OEE Lab Editorial |Updated 14 November 2026 |6 min read
Short answer

Downtime percentage = (total stop time / scheduled production time) x 100. Use the same time window for both numbers. Availability is the other side of it: availability = 100% minus downtime percentage, when every stop inside scheduled time is counted.

Downtime percentage calculator

Enter one machine or line over any period. The defaults are the shift worked through below. Updates as you type.

Time
min
Clock time of the period.
min
Breaks with no relief, no orders.
For calendar time, 24 h each.
Standard for OEE.
Downtime
Stops (2 to 10, an empty row is skipped)
Defaults: 480 min shift, 3 stops
Downtime percentage
-%
Downtime % = downtime ÷ time base × 100
0% = no stops100%
Downtime
-
Downtime hours
-
Uptime
-
Running
-
Unplanned
-
Planned
-
Time base
-
Top reason
-

How the time base splits

Downtime by reason

The working

Minutes are added first and divided once, so stops of any length weigh in by their minutes.

The formula

Downtime % = (downtime minutes / scheduled minutes) x 100
Scheduled minutes = shift minutes - excluded minutes
Availability % = 100 - downtime %
Downtime percentage

Scheduled time is the time the line was planned to make product. In OEE terms, it is total time minus excluded time. See Overall Equipment Effectiveness (R. C. Hansen, 2001) for the time model.

Downtime is every minute inside scheduled time when the line was not running. That includes breakdowns, changeovers, and waiting for material or people.

Hansen's book keeps the word downtime for unplanned stops and calls planned ones, such as changeovers, stop time. This page uses downtime for both, as most plants do.

Worked example

Example: an 8-hour shift is 480 minutes. A planned 30-minute break with no relief crew is not scheduled for production, so it is excluded. Scheduled time is 450 minutes.

The line logs three stops:

StopMinutesType
Breakdown35Unplanned
Changeover40Planned, normal running
Waiting for material25Unplanned
Total downtime100

Downtime % = 100 / 450 x 100 = 22.2%. Availability = 100 - 22.2 = 77.8%.

Check with runtime: 450 - 100 = 350 minutes, and 350 / 450 = 77.8%. Same answer.

Runtime350 min (77.8%)
Unplanned stops60 min (13.3%)
Planned changeover40 min (8.9%)
How the 450 scheduled minutes split. Runtime 350 minutes (77.8%), unplanned stops 60 minutes (13.3%), planned changeover 40 minutes (8.9%).

You can report one number or two. Unplanned downtime is 60 / 450 = 13.3%.

Planned downtime is 40 / 450 = 8.9%. Together they give 22.2%.

Showing both is better. The two have different owners. See planned vs unplanned downtime.

Which time do you divide by?

This is where most numbers go wrong. The same 100 minutes gives three different percentages.

Divide byCalculationResult
Scheduled time (standard for OEE)100 / 45022.2%
Shift length, break included100 / 48020.8%
A full 24-hour day100 / 1,4406.9%

Dividing by scheduled time answers: "of the time we planned to run, how much did we lose?" That is the figure that fits availability and OEE.

Dividing by the calendar answers a different question: "how much of the clock does downtime take?" It belongs with TEEP and capacity planning. See OEE vs TEEP.

Pick one and write it on the report. Never compare a percentage over scheduled time with one over calendar time.

How to combine several days

Do not average the daily percentages. Add the minutes first, then divide.

Example: two days on the same line.

DayScheduledDowntimeDowntime %
Monday, one shift45010022.2%
Tuesday, two shifts9009010.0%
Both days1,35019014.1%

The plain average of the two percentages is (22.2 + 10.0) / 2 = 16.1%. That is wrong, because Tuesday had twice the scheduled time.

The right figure is 190 / 1,350 = 14.1%. Overall Equipment Effectiveness (R. C. Hansen, 2001) gives the same rule for OEE: weight each period by its scheduled time.

Downtime percentage by cause

The total is the headline. The split by cause is the work list. Divide each cause by the same scheduled time.

Example: a week of five one-shift days. Scheduled time is 5 x 450 = 2,250 minutes.

CauseMinutes% of scheduled
Breakdowns2109.3%
Changeovers2008.9%
Waiting for material1506.7%
Waiting for an operator552.4%
Quality stops351.6%
Total65028.9%

9.3 + 8.9 + 6.7 + 2.4 + 1.6 = 28.9%, and 650 / 2,250 = 28.9%. The parts add up to the whole.

Now add money. Example: if each lost minute costs 50 euros in margin and labor, 650 minutes is 32,500 euros for the week. The 50 is an example, not a benchmark.

That figure is what gets a fix funded. A percentage alone rarely does.

What counts as downtime

  • Count it: breakdowns, changeovers, waiting for material, waiting for people, startup stops, quality stops.
  • Do not count it: excluded time, such as a planned shutdown set well ahead, time with no product scheduled, and holidays.
  • Leave it out of downtime, but do not forget it: speed loss and scrap. The line is running, so they are measured from counts. See speed losses.

Short stops matter here. If the log misses 30-second stops, the downtime percentage is too low and the speed loss is too high.

The sum stays the same, but the cause is wrong. See micro-stops.

A simple spreadsheet setup

  1. 1Make one row per stop. Columns: date, line, start, end, minutes, code, planned or unplanned.
  2. 2Make one row per shift for scheduled time. Shift length minus excluded minutes, with the reason for the exclusion noted.
  3. 3Sum the stop minutes per shift. A pivot table or a SUMIFS formula does it.
  4. 4Divide by scheduled minutes. Format the result as a percentage.
  5. 5Add a weekly total from the sums. Sum minutes, then divide. Never average the shift percentages.
Set it up once, reuse it every shift

The downtime log template has the stop rows ready. Keep the planned and unplanned flag in its own column, so you can split the percentage later without rework.

What to do with the number

  • Trend it. One week of 22.2% means little. A rise from 15% to 22% means a lot.
  • Rank the causes. Build a downtime Pareto chart of the minutes.
  • Put money on it. Multiply minutes by your cost per minute. The downtime cost calculator does this.
  • Put it in OEE. Availability from this page is the first of the three factors. See how to calculate OEE.

The same maths from the other side is on how to calculate uptime.

Common mistakes

  • Dividing by 24 hours when the line is scheduled for one shift.
  • Leaving the planned break inside the scheduled time.
  • Adding speed loss and scrap into "downtime".
  • Averaging percentages instead of adding minutes.
  • Comparing a line with a changeover every hour to one that runs for days, without splitting planned and unplanned.
See it live in Fabrico

Fabrico takes stops from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and shows OEE per line and shift, with the cause tagged by the operator at the line. The percentage is ready, with the minutes behind it. See how Fabrico shows downtime by line and shift.

Book a Fabrico demo

What people ask next

Is downtime percentage the same as 100% minus availability?

Yes, if downtime includes every stop inside scheduled time. If you leave out planned stops like changeover, you get unplanned downtime percentage instead, and availability will not be 100% minus that number.

Should planned downtime be in the percentage?

Report both. Planned stops such as changeover are real lost capacity, but they have a different owner than breakdowns. See planned vs unplanned downtime.

What is an acceptable downtime percentage?

It depends on the process, the product mix and how many changeovers you run. Compare with your own trend and fix the biggest cause first. Do not copy a target from another plant.

Do micro-stops count as downtime?

Yes, when they are recorded. If you cannot log them, they show up as speed loss, so the total loss is the same but the cause is hidden. See how to reduce micro-stops.

How do I turn downtime percentage into cost?

Find your cost per minute (lost margin, labor and fixed cost), then multiply it by the downtime minutes. The cost of downtime guide shows how.

Related guides: Unplanned Downtime Formula and KPI Calculation

← More OEE Lab guides · Open the OEE Calculator →