Machine efficiency usually means speed while running: actual rate ÷ rated speed. OEE multiplies that by availability and quality, over all scheduled time. A press can show 83.3% efficiency and 65.3% OEE in the same shift, and the machine with the better efficiency can make fewer good parts.
Machine efficiency has no fixed formula
This is where most of the confusion starts. "Machine efficiency" is a plant word, so ask how it is calculated before you compare it with anything.
You will usually see one of three versions, and only the last is OEE.
| Number | Formula | Sees stops? | Sees speed? | Sees bad parts? |
|---|---|---|---|---|
| Running efficiency | Actual rate / Rated speed | No | Yes | No |
| Efficiency on scheduled time | Output / (Rated speed x Scheduled time) | Yes | Yes | No |
| OEE | Good output / (Ideal rate x Scheduled time) | Yes | Yes | Yes |
A fourth use has nothing to do with this at all. An engineer may mean energy efficiency, as in a motor turning 95% of its power into work, and that says nothing about output.
One press, one shift, three numbers
Example: a press has an ideal rate of 30 strokes per minute, with one part per stroke. In a 480-minute shift it stops for 96 minutes, makes 9,600 parts and scraps 192.
Check the OEE with its factors. Availability is 384 ÷ 480 = 80.0%, performance is 83.3% and quality is 9,408 ÷ 9,600 = 98.0%, and those multiply to 65.3%.
So the three numbers are nested. The running efficiency is performance, efficiency on schedule is availability x performance, and OEE adds quality.
When efficiency picks the wrong machine
Here is why this matters for decisions. Take two presses with the same 30-per-minute ideal rate and the same 480-minute shift.
| Press X | Press Y | |
|---|---|---|
| Run time | 300 min | 432 min |
| Running efficiency | 95.0% | 80.0% |
| Availability | 62.5% | 90.0% |
| Quality | 99.0% | 99.0% |
| OEE | 58.8% | 71.3% |
| Good parts | about 8,465 | about 10,264 |
Judge by efficiency and press X wins by 15 points. Count good parts and press Y makes about 1,800 more.
Press X runs fast between long stops, and its efficiency report cannot see those stops. A team chasing that number might spend money on the wrong press.
Why the reverse trap also happens
Efficiency also depends on what you compare with. A rate set low years ago makes any machine look good, and readings above 100% are common.
That standard-based version is the subject of production efficiency vs OEE, so we will not repeat it here. OEE avoids the problem by using the ideal run rate, and by capping performance at 100%.
Overall equipment efficiency vs effectiveness
You will see OEE written both ways. Nakajima's tradition and Overall Equipment Effectiveness (R. C. Hansen, 2001) use "effectiveness", and that is the name used on this site.
"Efficiency" is also in real use, especially in chip making. Oechsner and colleagues (2002) use "overall equipment efficiency" in a paper on chip fabs, for the measure set out in the SEMI E79 standard.
In daily plant use, both names usually mean availability x performance x quality. There is a catch in the chip version, though.
A 2013 FabTime newsletter quotes V. A. Ames, who helped create E79, giving its simple formula as ideal time for good units over total time. That is closer to TEEP than to scheduled-time OEE.
So if a report says "overall equipment efficiency", check the time base. The word itself tells you less than the denominator does.
As plain English, the two words point at a real difference. Efficiency is about doing a thing with little waste, while effectiveness is about getting the result you wanted, and only OEE's quality factor checks for that.
Which number for which job
| Your question | Use |
|---|---|
| Is the machine running at its proper speed? | Running efficiency, or OEE performance |
| Should I look at settings, wear or material? | Running efficiency, by product |
| Which machine gives me the most good parts? | OEE |
| Where is my biggest loss? | OEE, broken into factors |
| Does the operator or the machine need help? | Neither alone, so look at the causes |
| How much of the machine's week am I using? | Utilization or TEEP |
Turn your efficiency report into OEE
You may already hold most of what you need. If your report gives a running efficiency, you only need two more figures.
The rated speed should be the best accredited rate, not an old standard.
Run time ÷ scheduled time, from a stop log or an hour meter.
Good parts ÷ total parts, then multiply all three.
If your running efficiency is calculated on "machine on" time, it may already hide short stops inside it. The guide to OEE performance shows how to work with that, and the OEE calculator does the multiplying.
When you first report OEE beside efficiency, expect questions, since the new number will be lower. Show the bars above with your own numbers, so people can see that the machine has not changed.
Many efficiency reports exist because a machine gives a speed but no stop record. Fabrico takes stops, speed and counts from PLCs or from external IoT sensors on older machines, so all three factors come from the same source. See how Fabrico connects to machines.
What people ask next
Is machine efficiency the same as OEE?
No. Machine efficiency usually covers speed while running, while OEE adds stops and quality over scheduled time. The closest match inside OEE is the performance factor, as availability vs performance vs quality explains.
Is OEE overall equipment efficiency or effectiveness?
The standard name in the TPM tradition is overall equipment effectiveness. Overall equipment efficiency also appears, especially in chip making. Either way, check the formula and the time base.
What is the formula for machine efficiency?
The most common form is actual rate ÷ rated speed while running. Some plants use output ÷ (rated speed x scheduled time) instead. Say which one you use, because they can differ by many points on the same shift.
Why is my machine efficiency higher than OEE?
Because efficiency leaves out some losses that OEE counts, usually stops and scrap. It can also rest on a lower standard rate. Start with production efficiency vs OEE if your number is above 100%.
Can machine efficiency be over 100%?
On a low standard rate, yes. Against a true ideal rate it should not be, so a reading over 100% means the rate is too low or the count is wrong. OEE performance is capped at 100% for that reason.