We found no standard or textbook that defines gross OEE and net OEE as a pair, so always ask for the formula. Plants usually mean this: gross OEE divides good output by the whole shift, and net OEE first removes planned time such as breaks. Net OEE, done honestly, is the standard OEE: good units x ideal cycle time ÷ scheduled time.
Gross vs net OEE calculator
Enter one shift. The defaults are the line worked through below. Updates as you type.
| Factor | Net | Gross |
|---|---|---|
| Time base | - | - |
| Availability | - | - |
| Performance | - | - |
| Quality | - | - |
| OEE | - | - |
What makes the gap
One shift, three time bases
The working
No standard defines gross and net OEE as a pair. This tool uses the readings described below, gross over the whole shift and net over scheduled time, so write your own rule down before you compare numbers.
A plain warning about these two terms
We looked for a source that sets out both terms and could not find one. Overall Equipment Effectiveness (R. C. Hansen, 2001) defines OEE on scheduled time, and neither term is part of the method this site follows from it.
So these are shop words, not defined measures. Two plants can both say "net OEE" and mean different sums.
Even the formal standards leave room. The abstract of Schiraldi and Varisco (2020) says ISO 22400 gives two OEE definitions that seem to differ from each other and from Nakajima's original.
The readings you will come across
| When someone says | They may mean | Divides by | Our view |
|---|---|---|---|
| Gross OEE | Good output against the whole paid shift | All shift minutes | A fair second number, if labeled |
| Net OEE | Good output after breaks and other time planned as no production | Scheduled time | This is standard OEE |
| Net OEE, loose version | Also takes out changeovers, setups or cleaning | Time left after all planned stops | Inflated, so avoid it |
| Net rate or net time | Nakajima's net operating rate, a part of performance | Run time | Not an OEE at all |
A person could also use "gross" for output before scrap and "net" for after it. Any number that leaves quality out is not OEE, so check that too.
Net OEE calculation, worked through
Example: a line has a 480-minute shift with a 30-minute break and a 15-minute planned meeting, and it does not run in either. Its ideal rate is 20 units per minute.
Inside the remaining time it has a 45-minute changeover and 40 minutes of other stops. It makes 5,880 units, and 5,760 are good.
Net OEE also passes the factor check. Availability is 350 ÷ 435 = 80.5%, performance is (5,880 ÷ 20) ÷ 350 = 84.0%, and quality is 5,760 ÷ 5,880 = 98.0%.
Multiply them and you get 66.2%. This is the same number both OEE methods should give you.
How the three versions compare on one shift
The third bar is the trap. A changeover is planned, but it is a step on the way to making product, so it stays in the schedule and lowers availability.
Take it out, and your number gains 7.6 points in an afternoon, while the line loses the same 45 minutes as before. It also stops showing any gain when you shorten changeovers.
The link between them
Gross and net are one calculation apart. Multiply net OEE by the share of the shift that was scheduled.
If you know this, gross OEE on a report is no threat. It just adds one more fact: how much of the paid shift was offered to production.
Stretch the time base to the whole calendar, and you have TEEP. A wider version with a staffed window is what some plants call OOE.
What each one rewards
The two numbers respond to different actions, and that is the real reason to look at both. Take the example and add a relief crew, so the line runs through the 30-minute break at the same mix of losses.
| Before | With relief crew | Change | |
|---|---|---|---|
| Scheduled time | 435 min | 465 min | +30 min |
| Run time | 350 min | 380 min | +30 min |
| Good output | 288.0 min | 312.7 min | +24.7 min |
| Gross OEE | 60.0% | 65.1% | +5.1 points |
| Net OEE | 66.2% | 67.2% | +1.0 point |
Gross OEE shows the capacity gain clearly, and net OEE barely moves. That is right for net OEE, since the line did not run any better while it was running.
So use net OEE to run the line better. Use gross or TEEP when the question is how many hours you get from the asset, and how to count breaks shows the rule on real cases.
What should go in each bucket
Most arguments here come down to one question. Was the time planned as not for production at all?
Take it out of scheduled time. Examples: a planned break with no relief, a planned meeting, a booked shutdown.
Keep it in. Examples: changeovers, start-up checks and material loading.
Keep it in. Examples: breakdowns, waiting for material and a break that overruns.
The guide to planned vs unplanned downtime goes through more cases. The tests follow Hansen's excluded time, and the OEE loss tree has a home for each minute.
What to put on the report
- Call the main number OEE. It needs no adjective, and it follows a known method.
- Print the denominator next to it. "66.2% of 435 scheduled minutes" cannot be misread.
- Show the excluded time as a line of its own. If it grows from 45 to 90 minutes a shift, someone should ask why.
- Keep one rule across lines. A plant average mixing the two versions means nothing, as averaging OEE shows.
If you compare with a benchmark, such as the 85% traced to Nakajima, use the same base. A loose net number makes the line look better than it is, and this guide to the 85% figure shows how to read it.
Disputes over net and gross usually start with loose stop records. Fabrico takes stops from the machine and operators tag the cause at the line, so stops carry a recorded reason you can rule on. See how Fabrico tracks stops.
What people ask next
What is the net OEE formula?
Net OEE = good units x ideal cycle time ÷ scheduled time, where scheduled time is the shift minus time planned as no production. It is the same as availability x performance x quality. No published source we found gives it a separate definition, so write yours down.
Which is higher, gross or net OEE?
Net OEE, or the two are equal, because its time base is smaller or the same. If net is far above gross, a lot of time is being taken out of the schedule, so check what is in there.
Should changeovers be taken out for net OEE?
No. A changeover is planned, but it stays in scheduled time and lowers availability. Taking it out hides a real loss and hides any gain you make, as how to count changeovers shows.
Is net OEE the same as NEE?
Not necessarily. NEE, or net equipment effectiveness, is another name without one settled definition, so ask for its formula as well. Compare it with net operating time, which is a different idea again.
Can I compare net OEE across plants?
Only after checking that the plants exclude the same things. A plant that takes out cleaning and setups will read higher with no better running. Set one written rule first, as in how to set OEE targets.
Fabrico is a light MES for OEE. It takes stops, speed and counts from PLCs or IoT sensors, with add-on AI cameras counting output where a machine has no usable signal, and operators tag the cause at the line.